R. Baker & Son Industrial Services Dismantles Cooling Towers at Active Facility

R. Baker & Son Industrial Services Dismantles Cooling Towers at Active Facility

R. Baker & Son All Industrial Services, a specialized dismantling, rigging and demolition contractor, completed the total dismantlement of two cooling towers at an active pharmaceutical plant in New Jersey. The work was part of a larger cooling tower replacement and upgrade project by Skanska USA Building.

The basic scope of work consisted of the total dismantlement of two wooden cooling towers that were approximately 60 feet high.  Each tower needed to be carefully dismantled, along with associated piping, stairs, hangers and supports, down to top of concrete dike slab. It was critical that the concrete slab of the dike not be damaged as this was going to be re-utilized for new construction.  The work also needed to be conducted with the utmost attention to safety for workers and the surrounding facility workers and nearby structures.  Active lines and structures were on all sides of the work area and also in close proximity to an active plant road with pedestrian and vehicular traffic.
Prior to any dismantling work being conducted, several important pre-dismantlement tasks needed to be completed.  All utilities and active lines to the cooling towers were isolated and made safe.  Asbestos containing materials were properly removed and abated.   As safety was paramount, chain link fencing with green screen mesh was placed around the work area.  In addition, debris netting was placed in strategic locations to ensure no debris landed outside the work zone.

Following these tasks, safety procedures and safety plans were implemented to ensure a safe dismantling project. Damon Kozul, PE, CHMM, Corp. Safety Officer, worked closely with Carl Finkelson, Project Manager, to ensure that safety was first and foremost on the project. A safety video was watched by all employees and each worker was instructed on the proper PPE required for the project.  Beyond the basic Level D PPE, high visibility safety vests were worn by all workers.  In addition, a JSA (Job Safety analysis) was developed and implemented for each day of work.

Dismantling of the two cooling towers started with the salvage of the fans for re-use and spare parts.  In order to rig this equipment safely, a Grove hydraulic 100-ton capacity all terrain crane was utilized.  R. Baker & Son assigned several of their key rigging experts, including T.J. Indelweiss and Mario Laka, to this phase of the project to ensure the task was completely safely and on schedule.  Under the management of Mr. Finkelson, the fan units were carefully extracted from the cooling tower units, rigged down without any damaged and then placed in the client’s storage area.

Following the equipment salvage, the interior of the dike for the cooling towers was cleaned of piping and all diffusers.  This selective demolition was done prior to any structural demo to make it easier to keep materials segregated for clean up and recycling.

Due to the proximity to active lines and structures, mechanical demolition using excavators could not be performed.  In order to safely take down the cooling towers, R. Baker & Son developed a methodology to utilize skilled dismantlers in manlifts with hand tools.  A 60 and 80 foot Genie manlift was lifted into the diked area using the 100-ton capacity crane.  The manlifts were then utilized by dismantlers with saws and other hand tools to methodically dismantle the wooden towers section by section.  As a section was demolished, debris was immediately removed using Bobcat S150 and S185 skid steers with demolition buckets.  This process continued until the concrete and steel base of the units was reached.

To demolish the concrete and steel beam bases, R. Baker & Son once again utilized the Grove 100-ton capacity crane to carefully lift equipment into the diked area.  Two (2) Bobcat 341 mini excavators with concrete breakers and buckets were utilized for this phase.  These machines easily demolished the cooling tower bases into rubble while not damaging the slab below which was to be utilized for the new construction.  The demolished concrete was loaded out of the diked area for offsite recycling.

The client had set a very demanding schedule that necessitated R. Baker & Son to work weekends.  Due to R. Baker & Son’s attention to pre-planning, safety implementation and the skilled workmanship by Mr. Finkelson’s crew, the project was safely completed on schedule.

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services is the premier specialized contractor for dismantlement, decommissioning and demolition in the United States, Canada and Puerto Rico.  The veteran owned company has been in business since 1935, has over 100 employees, an exemplary safety record (We have been directly involved in four (4) sites that received VPP OSHA Safety Awards) and is financially strong (bonding capabilities over $10 Million).  Capabilities include total plant and facility dismantlement, decommissioning, demolition, plant relocations and re-installations as well as heavy equipment rigging and machinery moving, millwright services and onsite concrete crushing.

Corporate Contact Information

R. Baker & Son All Industrial Services
1 Globe Street
Red Bank, NJ 07701
Phone: 732-222-3553
Fax: 732-450-0311
Website: www.rbaker.com

For more information visit our website or contact Damon Kozul, PE, CHMM at dkozul@rbaker.com

Full News Archive

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Interior Demolition Contractor in the North East
Quick Mobilization on Interior Demolition Project

Late last spring, construction was about to get underway on a large new warehouse in upstate New York when the construction management firm called R. Baker & Son with an urgent request. The...
interior demolition, mechanical contractor, installing prefabricated skids
Rigging Prefab in Sequence

At the completion of the interior demolition phase of a large renovation project, the mechanical contractor approached R. Baker & Son to request their assistance with rigging and installing...
Green Roof Installation - R. Baker & Son Environmental Services
Rigging Team Assists in Green Roof Installation

After a new office building construction project in western-central New Jersey where R. Baker & Son had been rigging architectural features in the expansive atrium, the construction manager asked...
Demolition Day T-Shirt, R. Baker Demolition
Everyone Loves Demolition Day!

Back in the mid-1940s, the demolition wrecking ball was a unique new demolition tool. A massive heavy steel ball swung by a very skillful operator in a large crane. By carefully moving the crane and...
Logistics are vital to plant relocation project
Successful Plant Relocation

Relocating a plant is a highly demanding task, but a large portion of the work happens in the planning.Plant relocation projects must be handled through a master plan with multiple phases and...
R. Baker & Son All Industrial Services Warehouse
Storing and Rigging Specialized Bio-Equipment for New Laboratory

A biomedical research firm in upstate New York reached out to R. Baker & Son for assistance with a special project. Two areas of a 40,000 square foot research building were to be phased out to...
Abandoned Industrial Building Demolition
Reuse & Value Engineering

R. Baker & Son has nearly 85 years of experience helping customers save money on projects. One approach is to reuse existing building equipment, materials, furnishings, and architectural...
450 ton energy-efficient centrifugal chillers
Rigging and Assembly on HVAC Upgrade Project

Last winter, R. Baker & Son took part in several HVAC energy upgrade projects on four air handling units ranging from 30,000 to 50,000 CFM at a Northern New Jersey hospital, as well as the...