All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Interior Demo: Mid-Project Changes Save Time and Money

Interior Demolition - Wet Saw

Discovering an opportunity for substantial cost savings during a project in progress is always a welcome surprise, which was the case on a warehouse renovation in which R. Baker & Son was tasked with performing the   of the 200,000 sq. ft. building. The building was to become a manufacturing plant with 10,000 square feet of offices occupying one corner and heavy mechanical areas throughout the facility. 

Phase one of the interior demolition project was fairly standard. After careful planning and coordination of utility shutoff, everything within the building’s four outer walls and roof were removed using equipment that included forklifts, loaders, and skid steers brought in through existing loading dock doors. R. Baker & Son also handled reclamation and resale of an existing generator and multiple transfer switches to help offset some of the demolition costs. 

The second phase of demolition was saw-cutting and removal of approximately 50,000 sq. ft. of the concrete floor slab to accommodate the new plant’s underground sanitary and process plumbing. It was during this time that it became clear that, with some careful planning and cutting of an addition 4,000 sq. ft. of slab by the Baker Team, much of the overhead electrical conduit and cable tray could be relocated below ground fairly easily, saving a considerable amount of money in labor and material. Not having racks of conduit suspended from the ceiling or cable tray with miscellaneous steel supports would also result in a much cleaner, more aesthetically-pleasing installation. 

R. Baker & Son worked closely with plumbing and electrical contractors throughout the BIM coordination process for precisely relocating, trenching and backfilling all pipe and conduit. These changes resulted in savings of $112,000 and four weeks were shaved from the overall master schedule. With a tight budget, aggressive schedule and cost overruns in other areas of the project, this was music to the owners’ ears.

Full News Archive

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Warehouse Demolition, NYC Emergency Service Call
Emergency Warehouse Demolition

The owner of a 25,000 square foot Brooklyn warehouse was in a serious bind. A wall and part of the roof of the recently-vacated building had unexpectedly collapsed, and the remaining walls appeared...
riggers and millwrights, lyophilizer
Rigging & Assembly Teams Install Pharma Fill Line

R. Baker & Son was contracted by a long-time client to install a large vial fill line with a Class 100 environmental tunnel with a large lyophilizer and auto-loader system. This entailed rigging...
Rigging & Building Information Modeling
Planning A Rigging Project w/ BIM

R. Baker & Son worked closely with a client and their design firm to get upfront budget pricing for rigging building and process equipment on a large process manufacturing facility project. The...
curtain wall demolition contractor NYC
Expert in NYC Curtain Wall Dismantling and Demolition

Ever since construction of the glass-clad United Nations Secretariat Building was completed in 1952, skyscrapers encased in sparkling glass curtain walls have come to dominate the New York City...
Safety Plan, Demolition and Rigging Contractor
Site-Specific Safety Plan

A site-specific safety plan (SSSP) is an agreement that addresses project-specific safety concerns and challenges and how to manage them. It serves as a communication tool between involved...
Preventing, Recognizing, and Treating Heat Related Illness
R. Baker Workers Trained In Heat Related Illness

With summer only just begun, there are likely many hot days ahead. In construction, demolition, and rigging, heat-related illness is a very real threat if the proper steps are not taken to prevent...
Tank Rigging Project - All Industrial Services
Tank Rigging Project

A large food processing plant was referred to R. Baker & Son to take on the task of rigging all new equipment into an existing 200,000 sq. ft. facility. The majority of equipment consisted of...
Skid Steer Loader - Demolition Contractor
The Skid Steer Loader, Workhorse of the Demolition Industry

One of the most versatile machines on any construction or demolition project is the skid steer loader, a compact, rigid-framed, engine-powered machine with lift arms that can be fitted with a variety...