All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Interior Demo: Mid-Project Changes Save Time and Money

Interior Demolition - Wet Saw

Discovering an opportunity for substantial cost savings during a project in progress is always a welcome surprise, which was the case on a warehouse renovation in which R. Baker & Son was tasked with performing the   of the 200,000 sq. ft. building. The building was to become a manufacturing plant with 10,000 square feet of offices occupying one corner and heavy mechanical areas throughout the facility. 

Phase one of the interior demolition project was fairly standard. After careful planning and coordination of utility shutoff, everything within the building’s four outer walls and roof were removed using equipment that included forklifts, loaders, and skid steers brought in through existing loading dock doors. R. Baker & Son also handled reclamation and resale of an existing generator and multiple transfer switches to help offset some of the demolition costs. 

The second phase of demolition was saw-cutting and removal of approximately 50,000 sq. ft. of the concrete floor slab to accommodate the new plant’s underground sanitary and process plumbing. It was during this time that it became clear that, with some careful planning and cutting of an addition 4,000 sq. ft. of slab by the Baker Team, much of the overhead electrical conduit and cable tray could be relocated below ground fairly easily, saving a considerable amount of money in labor and material. Not having racks of conduit suspended from the ceiling or cable tray with miscellaneous steel supports would also result in a much cleaner, more aesthetically-pleasing installation. 

R. Baker & Son worked closely with plumbing and electrical contractors throughout the BIM coordination process for precisely relocating, trenching and backfilling all pipe and conduit. These changes resulted in savings of $112,000 and four weeks were shaved from the overall master schedule. With a tight budget, aggressive schedule and cost overruns in other areas of the project, this was music to the owners’ ears.

Full News Archive

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

R. Baker Industrial Worker With Laptop At Demolition Project
Precision Planning in Construction Demolition

When it comes to defining a construction project's approach, most proficient project management teams can produce a plan that methodically lays out phases, tasks, and timelines in meticulous...
interior demolition at a manufacturing and production facility, rigging crew
Precision MEP Install at a South Jersey Manufacturing Facility

As part of a 150,000 sq/ft manufacturing and production facility renovation project in South Jersey, R Baker had completed the selective interior demolition work months before. This work included...
Precision Demolition Equipment
Precision Demolition: R. Baker & Son's Advanced Equipment & Techniques

When tackling the complexities of industrial demolition, you're not just swinging a wrecking ball. At R. Baker & Son, we understand that precision, safety, and efficiency are paramount....
R. Baker & Son Crane used in plant relocation
Comprehensive Guide to Plant Relocation: Planning for Success

Strategic Planning: The Foundation of Plant Relocation Plant relocation represents a complex logistical challenge where success hinges primarily on thorough planning. A comprehensive master plan...
How Virtual Reality is Changing Riggers Training
How Virtual Reality is Changing Riggers Training

Using virtual reality (VR) in training for rigging professionals offers a multitude of benefits that enhance the learning experience and improve safety and efficiency in the field. Here are some key...
Chemical Bursting: Concrete Demolition
Chemical Bursting: The Silent Revolution in Concrete Demolition

While traditional concrete demolition often relies on hydraulic breakers, pneumatic drills, saw cutting, and explosives, some projects demand more subtle approaches. Chemical bursting, also known as...
Demolition and Rigging: A Half Century of Safety Innovation
Demolition and Rigging: A Half Century of Safety Innovation

Safety stands as the cornerstone of everything we do at R Baker and Son's demolition and rigging operations. Those of us with decades of experience in the field understand the importance of...
Toolbox Talks, R. Baker & Son Demolition Crew
Safety Through Dialogue: The Critical Role of Toolbox Talks

Toolbox talks are a cornerstone of effective company safety programs. These informal safety meetings, typically held on job sites before work begins, focus on specific safety topics and are designed...