All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Interior Demo: Mid-Project Changes Save Time and Money

Interior Demolition - Wet Saw

Discovering an opportunity for substantial cost savings during a project in progress is always a welcome surprise, which was the case on a warehouse renovation in which R. Baker & Son was tasked with performing the   of the 200,000 sq. ft. building. The building was to become a manufacturing plant with 10,000 square feet of offices occupying one corner and heavy mechanical areas throughout the facility. 

Phase one of the interior demolition project was fairly standard. After careful planning and coordination of utility shutoff, everything within the building’s four outer walls and roof were removed using equipment that included forklifts, loaders, and skid steers brought in through existing loading dock doors. R. Baker & Son also handled reclamation and resale of an existing generator and multiple transfer switches to help offset some of the demolition costs. 

The second phase of demolition was saw-cutting and removal of approximately 50,000 sq. ft. of the concrete floor slab to accommodate the new plant’s underground sanitary and process plumbing. It was during this time that it became clear that, with some careful planning and cutting of an addition 4,000 sq. ft. of slab by the Baker Team, much of the overhead electrical conduit and cable tray could be relocated below ground fairly easily, saving a considerable amount of money in labor and material. Not having racks of conduit suspended from the ceiling or cable tray with miscellaneous steel supports would also result in a much cleaner, more aesthetically-pleasing installation. 

R. Baker & Son worked closely with plumbing and electrical contractors throughout the BIM coordination process for precisely relocating, trenching and backfilling all pipe and conduit. These changes resulted in savings of $112,000 and four weeks were shaved from the overall master schedule. With a tight budget, aggressive schedule and cost overruns in other areas of the project, this was music to the owners’ ears.

Full News Archive

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

R. Baker & Son riggers installing 24 pharmaceutical bioreactors with platforms and safety railings in upstate New York facility
How We Installed 24 Bioreactors in Just 4 Weeks (NY Pharma)

R. Baker & Son recently completed a complex pharmaceutical equipment installation project after receiving a referral from a senior process engineer at a leading New Jersey design firm. The...
Professional Rigging Services: Expert Equipment Handling and Installation to Avoid Costly Damage
Professional Rigging: Why Equipment Installation Requires Expert Expertise

Comprehensive Rigging Services Across Industries R Baker & Son's rigging teams collaborate with equipment manufacturers across virtually every major industry. This extensive experience...
Professional building demolition with hydraulic shear in urban setting
Professional Building Demolition: Why Structural Knowledge Matters

To be successful in professional building demolition and dismantling, you need to be an experienced demolition expert in taking buildings down - whether in whole, in part, or in pieces. Providing...
Strategic demolition of industrial warehouse for brownfield redevelopment into sustainable community space in urban renewal project
Demolition & Brownfield Redevelopment: Sustainable Urban Renewal

One of the greatest environmental impacts we can make comes through the strategic demolition and brownfield redevelopment process. This powerful combination represents far more than simple building...
Crane rigging sets construction trailers at NJ hospital renovation site
Rigging Streamlines NJ Hospital Renovation Mobilization

Getting a new project up and running requires planning, organization, and detailed layout, all of which must be done quickly and efficiently. This was certainly the case when one of our clients, a CM...
Demolition Equipment in the field, R. Baker & Son
Sustainable Demolition Services: R Baker's Lean Meets Green Approach

Over our 90 years in business, R. Baker & Son has witnessed tremendous changes and progress in the demolition industry. Today's demolition work presents unique challenges and opportunities...
Warehousing and industrial rigging services for plant relocation.
Plant Relocation Services: Planning & Production | R. Baker & Son

The decision to relocate a manufacturing facility represents one of the most significant undertakings a company can face. Success hinges on expert project management, strategic planning, and seamless...
Rigging equipment ready for a heavy lift, NYC, NJ
Industrial Rigging NYC & NJ: Choosing Your Urban Partner

New York City and New Jersey's iconic skylines? They're pure proof of incredible construction and engineering. But peel back the layers of every towering building and complex industrial spot,...