All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Substation & Mechanical Selective Demolition: Out With the Old

Substation and Mechanical Selective Demolition

A new pharmaceutical company took over an existing North Jersey facility with plans for major demolition and renovation. Design work began immediately, and long-lead equipment was ordered early on. To meet the aggressive schedule, a parallel selective demolition plan was developed by R. Baker & Son in anticipation of the arrival of the new equipment. 

Plans called for a new, larger electrical service requiring removal of an existing substation and installation of a new one. Two existing 600 HP boilers were slated for removal to make way for eight smaller high-efficiency boilers. Four 75-ton chillers, only five years old, were to remain, but aged 100% outside air handlers and associated piping were to be replaced by new recirculating units and required demolition. Because the facility was to be operational for the duration of the project, however, it was necessary for utilities and HVAC systems remain in place until new equipment arrived, at which point R. Baker & Son’s portion of the project would need to move forward swiftly. This required a close team effort between the Baker team, electrical and mechanical contractors, and the owner.  

The first, and most critical, swap-out was the removal of a 1500 kVA single-ended substation and installation of a 2500 kVA double-ended substation on a newly-enlarged concrete pad. After weeks of planning and preparation, the electrical shutdown began on a Friday night.  Following all lockout-tagout procedures, the equipment removal proceeded through the weekend. The new substation was rigged in place on Monday morning, and reconnection began immediately, with a one-week timeframe to get the power back on. 

Over the next several consecutive Fridays, R. Baker & Son removed the two existing boilers so the eight smaller boilers could be rigged, set, installed in place, and readied for piping. Finally, the air handlers were removed in a set sequence to keep the cooling system running while the new units were installed.  The Baker team performed asset recovery of the boilers and substations for resale allowed the owner to recoup their value and reduce the overall cost of the project.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553
http://rbaker.com/selective-demolition.php

Full News Archive

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

interior demolition, mechanical contractor, installing prefabricated skids
Rigging Prefab in Sequence

At the completion of the interior demolition phase of a large renovation project, the mechanical contractor approached R. Baker & Son to request their assistance with rigging and installing...
Green Roof Installation - R. Baker & Son Environmental Services
Rigging Team Assists in Green Roof Installation

After a new office building construction project in western-central New Jersey where R. Baker & Son had been rigging architectural features in the expansive atrium, the construction manager asked...
Demolition Day T-Shirt, R. Baker Demolition
Everyone Loves Demolition Day!

Back in the mid-1940s, the demolition wrecking ball was a unique new demolition tool. A massive heavy steel ball swung by a very skillful operator in a large crane. By carefully moving the crane and...
Logistics are vital to plant relocation project
Successful Plant Relocation

Relocating a plant is a highly demanding task, but a large portion of the work happens in the planning.Plant relocation projects must be handled through a master plan with multiple phases and...
R. Baker & Son All Industrial Services Warehouse
Storing and Rigging Specialized Bio-Equipment for New Laboratory

A biomedical research firm in upstate New York reached out to R. Baker & Son for assistance with a special project. Two areas of a 40,000 square foot research building were to be phased out to...
Abandoned Industrial Building Demolition
Reuse & Value Engineering

R. Baker & Son has nearly 85 years of experience helping customers save money on projects. One approach is to reuse existing building equipment, materials, furnishings, and architectural...
450 ton energy-efficient centrifugal chillers
Rigging and Assembly on HVAC Upgrade Project

Last winter, R. Baker & Son took part in several HVAC energy upgrade projects on four air handling units ranging from 30,000 to 50,000 CFM at a Northern New Jersey hospital, as well as the...
Rigging Contractor, Crane, NY,NJ, R. Baker & Son
Fundamentals of Rigging

When it comes to crane rigging, there are a number of fundamental procedures that must be followed. R. Baker & Son is one of the nation’s top rigging contractors, with extensive knowledge...