All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Substation & Mechanical Selective Demolition: Out With the Old

Substation and Mechanical Selective Demolition

A new pharmaceutical company took over an existing North Jersey facility with plans for major demolition and renovation. Design work began immediately, and long-lead equipment was ordered early on. To meet the aggressive schedule, a parallel selective demolition plan was developed by R. Baker & Son in anticipation of the arrival of the new equipment. 

Plans called for a new, larger electrical service requiring removal of an existing substation and installation of a new one. Two existing 600 HP boilers were slated for removal to make way for eight smaller high-efficiency boilers. Four 75-ton chillers, only five years old, were to remain, but aged 100% outside air handlers and associated piping were to be replaced by new recirculating units and required demolition. Because the facility was to be operational for the duration of the project, however, it was necessary for utilities and HVAC systems remain in place until new equipment arrived, at which point R. Baker & Son’s portion of the project would need to move forward swiftly. This required a close team effort between the Baker team, electrical and mechanical contractors, and the owner.  

The first, and most critical, swap-out was the removal of a 1500 kVA single-ended substation and installation of a 2500 kVA double-ended substation on a newly-enlarged concrete pad. After weeks of planning and preparation, the electrical shutdown began on a Friday night.  Following all lockout-tagout procedures, the equipment removal proceeded through the weekend. The new substation was rigged in place on Monday morning, and reconnection began immediately, with a one-week timeframe to get the power back on. 

Over the next several consecutive Fridays, R. Baker & Son removed the two existing boilers so the eight smaller boilers could be rigged, set, installed in place, and readied for piping. Finally, the air handlers were removed in a set sequence to keep the cooling system running while the new units were installed.  The Baker team performed asset recovery of the boilers and substations for resale allowed the owner to recoup their value and reduce the overall cost of the project.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553
http://rbaker.com/selective-demolition.php

Full News Archive

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Cooling Tower Dismantling Project
University Cooling Tower Dismantling Project

A large Staten Island mechanical contractor contacted R. Baker & Son to remove a 1,000-ton cooling tower at a university to make way for a new high-efficiency tower and filtration system. The...
Danger sign for rigging, dismantling & demolition site
Rigging, Dismantling & Demolition Project Safety

Safety is the number one priority on every R. Baker & Son project, from dismantling, rigging, and demolition, to plant decommissioning, plant relocation, and environmental services. Safeguards...
construction worker performing a multi heat exchanger changeout 
Baker Performs Multi Heat Exchanger Changeout

Back in early 2021, R. Baker & Son took part in a food manufacturing construction project in which we performed rigging and assembly of six large, high-pressure steam ovens over a ten-week...
Pre-construction, tablet on table of demolition contractor.
Preconstruction Services

The goal on every construction, renovation or demolition project is to have experienced, reputable contractors bid the project competitively. Preconstruction services, often referred to as precon,...
Asset Recovery: Refurbished Parts and Equipment in High Demand
Asset Recovery: Refurbished Parts and Equipment in High Demand

With supply chain shortages and inflation continuing into 2022, the demand for reconditioned parts and equipment is on the rise. Investment recovery, also known as asset recovery, of aged equipment...
Generator Replacement
Weekend Standby Generator Replacement

A large laboratory and office complex needed to replace an existing standby generator with a new, larger 2000 kW unit with associated automatic transfer switches and day tank. The owner needed the...
Rigging Project - Mechanical Room and Equipment
R. Baker & Son: Rigging Project Consultation

A longtime R. Baker & Son client approached us to help out on a very large project that was being proposed by one of the construction company’s satellite offices in Virginia. The project...
Interior Demolition: Epoxy Floor Removal Project
Interior Demolition: Epoxy Floor Removal

R. Baker & Son was contracted to perform interior demolition at a New Jersey pharmaceuticals manufacturing plant. Originally built in 1948, the second floor of the two-story building had served...