All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Innovative Plan in Manhattan High Rise Project

56 Leonard Street

By the time construction of 56 Leonard, an iconic new residential skyscraper located in the Tribeca section of Manhattan, wrapped up late last year, all of its 145 luxury units had sold out, some going for prices as high as $48 million. Known as the Jenga Tower due to its stunning and unusual appearance, the glass-encased 60-story building features a staggered silhouette of shifting and varying floorplates, cantilevers, and balconies. Not surprisingly, construction of 56 Leonard was exceptionally complex, even by New York City standards, which was recognized last month when ENR New York named 56 Leonard 2017’s Best Project in the Residential/Hospitality category.  

R. Baker & Son took on one of the challenging project’s early hurdles: the removal of massive steel I-beams cantilevered 25 feet over the roof of an adjacent building. The falsework beams were installed on the 6th floor to provide temporary structural support until the concrete had sufficiently cured while construction progressed on the floors above. R. Baker & Son was challenged to develop an innovative plan to remove the huge beams safely and efficiently. Taking into account the many complex logistical challenges of the project, Baker engineers determined that beam sections would need to be cut and removed from the structure’s interior, rather from the exposed ends jutting from the building.  After hours of brainstorming, the Baker team came up with a unique and inventive solution that would provide the key to the project: custom-fabricated weighted dollies that would be used to slide the beams inward while serving as counterweights. 

The removal procedure began with Baker team members fabricating steel guides around each I-beam and securing them to nearby concrete columns. After attaching two heavily-weighted dollies to each beam, workers would cut a 4-foot section, each weighing 1,200 lbs., from the interior end of the I-beam. The dollies/counterweights prevented the cantilevered ends of the beams from tipping past the fulcrum point when the sections were detached. Each time a section was removed, Baker crew members used heavy-duty winches to wheel the remaining beam another four feet into the building. Then everything would be repositioned and the entire process would be repeated. The removed sections were stacked three high, and workers utilized an in-house material hoist to lower the 3,600-lb. stacks to ground level. 

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553http://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

rigging project planning, man welding steel beams
Expert Rigging: Meticulous Planning for Safe Lift Projects

A major rigging project demands meticulous planning and execution. While the actual lift may only span a day or two, it represents the culmination of weeks or even months of intense...
Rigging Equipment, skyline NYC, Women Owned Business
Efficient Rigging and Equipment Setup: Planning and Collaboration

R. Baker & Son was contacted by a large mechanical contractor with whom we have worked in the past and who works in the New Jersey-Philadelphia area. They had a large renovation project that...
Environmental Solutions for Dismantling, Decommissioning and Demolition
Eco-Friendly Solutions for Dismantling, Demo & Decommissioning

Demolition, dismantling, or decommissioning of industrial facilities is a complex process that requires meticulous planning and execution. These sites often contain hazardous chemicals, substances,...
Selective Demolition and Rigging at Process Plant
Selective Demolition and Rigging at Process Plant

R. Baker & Son recently performed selective demolition and equipment rigging for a process plant construction project. The selective demolition was necessary to prepare the existing facility to...
Chiller and Cooling Tower Installation at a South Jersey Hospital
Rigging Success: Chiller & Cooling Tower Installation at Jersey Hospital

Recently, R. Baker & Son team was faced with the task of installing a new 1200-ton chiller and double cell cooling tower at a South Jersey hospital. The project was referred to us by a trusted...
Industrial Workers Rigging 2024
Celebrating a New Year from R. Baker & Son

As a new year begins, we reflect on our deep appreciation for all our employees, associates, contractors, vendors, and customers. Our founder, Ruby Baker, started R. Baker & Son in 1935 during...
Define Demolition Scope and Budget
Maximizing Your Demolition Project - Tips to Define Scope|Budget

Often on large construction and renovation projects, the demolition portion of the Scope of Work is vague or poorly defined. It’s not uncommon to see a boxed-out area on drawings with only a...
Demolition in New York,
Industrial Demolition in NYC: A Look at the Process and Impact

When it comes to industrial demolition in NYC, R. Baker & Son has been trusted for well over 80years. With their expertise, experience, and commitment to safety, they have become one of the most...