All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Innovative Plan in Manhattan High Rise Project

56 Leonard Street

By the time construction of 56 Leonard, an iconic new residential skyscraper located in the Tribeca section of Manhattan, wrapped up late last year, all of its 145 luxury units had sold out, some going for prices as high as $48 million. Known as the Jenga Tower due to its stunning and unusual appearance, the glass-encased 60-story building features a staggered silhouette of shifting and varying floorplates, cantilevers, and balconies. Not surprisingly, construction of 56 Leonard was exceptionally complex, even by New York City standards, which was recognized last month when ENR New York named 56 Leonard 2017’s Best Project in the Residential/Hospitality category.  

R. Baker & Son took on one of the challenging project’s early hurdles: the removal of massive steel I-beams cantilevered 25 feet over the roof of an adjacent building. The falsework beams were installed on the 6th floor to provide temporary structural support until the concrete had sufficiently cured while construction progressed on the floors above. R. Baker & Son was challenged to develop an innovative plan to remove the huge beams safely and efficiently. Taking into account the many complex logistical challenges of the project, Baker engineers determined that beam sections would need to be cut and removed from the structure’s interior, rather from the exposed ends jutting from the building.  After hours of brainstorming, the Baker team came up with a unique and inventive solution that would provide the key to the project: custom-fabricated weighted dollies that would be used to slide the beams inward while serving as counterweights. 

The removal procedure began with Baker team members fabricating steel guides around each I-beam and securing them to nearby concrete columns. After attaching two heavily-weighted dollies to each beam, workers would cut a 4-foot section, each weighing 1,200 lbs., from the interior end of the I-beam. The dollies/counterweights prevented the cantilevered ends of the beams from tipping past the fulcrum point when the sections were detached. Each time a section was removed, Baker crew members used heavy-duty winches to wheel the remaining beam another four feet into the building. Then everything would be repositioned and the entire process would be repeated. The removed sections were stacked three high, and workers utilized an in-house material hoist to lower the 3,600-lb. stacks to ground level. 

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553http://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Interior Demolition Contractor in the North East
Quick Mobilization on Interior Demolition Project

Late last spring, construction was about to get underway on a large new warehouse in upstate New York when the construction management firm called R. Baker & Son with an urgent request. The...
interior demolition, mechanical contractor, installing prefabricated skids
Rigging Prefab in Sequence

At the completion of the interior demolition phase of a large renovation project, the mechanical contractor approached R. Baker & Son to request their assistance with rigging and installing...
Green Roof Installation - R. Baker & Son Environmental Services
Rigging Team Assists in Green Roof Installation

After a new office building construction project in western-central New Jersey where R. Baker & Son had been rigging architectural features in the expansive atrium, the construction manager asked...
Demolition Day T-Shirt, R. Baker Demolition
Everyone Loves Demolition Day!

Back in the mid-1940s, the demolition wrecking ball was a unique new demolition tool. A massive heavy steel ball swung by a very skillful operator in a large crane. By carefully moving the crane and...
Logistics are vital to plant relocation project
Successful Plant Relocation

Relocating a plant is a highly demanding task, but a large portion of the work happens in the planning.Plant relocation projects must be handled through a master plan with multiple phases and...
R. Baker & Son All Industrial Services Warehouse
Storing and Rigging Specialized Bio-Equipment for New Laboratory

A biomedical research firm in upstate New York reached out to R. Baker & Son for assistance with a special project. Two areas of a 40,000 square foot research building were to be phased out to...
Abandoned Industrial Building Demolition
Reuse & Value Engineering

R. Baker & Son has nearly 85 years of experience helping customers save money on projects. One approach is to reuse existing building equipment, materials, furnishings, and architectural...
450 ton energy-efficient centrifugal chillers
Rigging and Assembly on HVAC Upgrade Project

Last winter, R. Baker & Son took part in several HVAC energy upgrade projects on four air handling units ranging from 30,000 to 50,000 CFM at a Northern New Jersey hospital, as well as the...