All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Innovative Plan in Manhattan High Rise Project

56 Leonard Street

By the time construction of 56 Leonard, an iconic new residential skyscraper located in the Tribeca section of Manhattan, wrapped up late last year, all of its 145 luxury units had sold out, some going for prices as high as $48 million. Known as the Jenga Tower due to its stunning and unusual appearance, the glass-encased 60-story building features a staggered silhouette of shifting and varying floorplates, cantilevers, and balconies. Not surprisingly, construction of 56 Leonard was exceptionally complex, even by New York City standards, which was recognized last month when ENR New York named 56 Leonard 2017’s Best Project in the Residential/Hospitality category.  

R. Baker & Son took on one of the challenging project’s early hurdles: the removal of massive steel I-beams cantilevered 25 feet over the roof of an adjacent building. The falsework beams were installed on the 6th floor to provide temporary structural support until the concrete had sufficiently cured while construction progressed on the floors above. R. Baker & Son was challenged to develop an innovative plan to remove the huge beams safely and efficiently. Taking into account the many complex logistical challenges of the project, Baker engineers determined that beam sections would need to be cut and removed from the structure’s interior, rather from the exposed ends jutting from the building.  After hours of brainstorming, the Baker team came up with a unique and inventive solution that would provide the key to the project: custom-fabricated weighted dollies that would be used to slide the beams inward while serving as counterweights. 

The removal procedure began with Baker team members fabricating steel guides around each I-beam and securing them to nearby concrete columns. After attaching two heavily-weighted dollies to each beam, workers would cut a 4-foot section, each weighing 1,200 lbs., from the interior end of the I-beam. The dollies/counterweights prevented the cantilevered ends of the beams from tipping past the fulcrum point when the sections were detached. Each time a section was removed, Baker crew members used heavy-duty winches to wheel the remaining beam another four feet into the building. Then everything would be repositioned and the entire process would be repeated. The removed sections were stacked three high, and workers utilized an in-house material hoist to lower the 3,600-lb. stacks to ground level. 

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553http://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Process Tank Repair Project, R. Baker & Son
R. Baker & Son Process Tank Repair Project

A longtime R. Baker & Son client with several large process tank farms at their New Jersey facility contacted us for assistance with tank repairs. A manufacturer supplying tank agitators needed...
Provides a Wide Range of Environmental Services, R. Baker & Son
R. Baker & Son Provides a Wide Range of Environmental Services

Included among R. Baker & Son’s core services are environmental remediation and decontamination. We boast a team of highly-trained environmental remediation personnel as well as an arsenal...
selective demolition in hospitals
Requirements of Selective Demolition in Healthcare Facilities

Some of the most challenging selective demolition jobs are renovation projects that take place in healthcare facilities, where demolition team members must be specially trained to work in sensitive...
 Plant Demolition and Demolition Contractor Services
R. Baker & Son Demo Team Completes Partial Plant Demolition

R. Baker & Son recently completed a demolition and decommissioning project at a northern New Jersey plant. The first of R. Baker & Son’s tasks was to demolish a 60’ x 30’...
Rigging and Anchoring Heavy Machinery and Equipment
Rigging and Anchoring Heavy Machinery and Equipment

An important work scope that is often overlooked on construction projects is the rigging and anchoring of equipment to concrete, steel platforms, curbs, decking, etc. Anchoring should not be an...
Completes Selective Demolition Project on Christmas Eve
Baker Completes Selective Demolition Project on Christmas Eve

Over the recent winter holiday season, R. Baker & Son was tasked with performing selective demolition at a medical manufacturing facility that produced orthopedic titanium parts and hardware....
Rigging Project Using Building Information Modeling
3D Rigging Using BIM

R. Baker & Son was recently engaged in a complex project in which we were tasked with rigging and setting numerous pieces of process equipment from more than thirty different vendors. Items...
Rigging Project
Stainless Steel Tank Rigging Project Saved by Plan B

Progress on a construction site can sometimes be thwarted when new equipment or materials arrive with problems. Sometimes, no matter how much planning went into a project, one or two obstacles can...