All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Innovative Plan in Manhattan High Rise Project

56 Leonard Street

By the time construction of 56 Leonard, an iconic new residential skyscraper located in the Tribeca section of Manhattan, wrapped up late last year, all of its 145 luxury units had sold out, some going for prices as high as $48 million. Known as the Jenga Tower due to its stunning and unusual appearance, the glass-encased 60-story building features a staggered silhouette of shifting and varying floorplates, cantilevers, and balconies. Not surprisingly, construction of 56 Leonard was exceptionally complex, even by New York City standards, which was recognized last month when ENR New York named 56 Leonard 2017’s Best Project in the Residential/Hospitality category.  

R. Baker & Son took on one of the challenging project’s early hurdles: the removal of massive steel I-beams cantilevered 25 feet over the roof of an adjacent building. The falsework beams were installed on the 6th floor to provide temporary structural support until the concrete had sufficiently cured while construction progressed on the floors above. R. Baker & Son was challenged to develop an innovative plan to remove the huge beams safely and efficiently. Taking into account the many complex logistical challenges of the project, Baker engineers determined that beam sections would need to be cut and removed from the structure’s interior, rather from the exposed ends jutting from the building.  After hours of brainstorming, the Baker team came up with a unique and inventive solution that would provide the key to the project: custom-fabricated weighted dollies that would be used to slide the beams inward while serving as counterweights. 

The removal procedure began with Baker team members fabricating steel guides around each I-beam and securing them to nearby concrete columns. After attaching two heavily-weighted dollies to each beam, workers would cut a 4-foot section, each weighing 1,200 lbs., from the interior end of the I-beam. The dollies/counterweights prevented the cantilevered ends of the beams from tipping past the fulcrum point when the sections were detached. Each time a section was removed, Baker crew members used heavy-duty winches to wheel the remaining beam another four feet into the building. Then everything would be repositioned and the entire process would be repeated. The removed sections were stacked three high, and workers utilized an in-house material hoist to lower the 3,600-lb. stacks to ground level. 

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553http://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Cooling Tower Dismantling Project
University Cooling Tower Dismantling Project

A large Staten Island mechanical contractor contacted R. Baker & Son to remove a 1,000-ton cooling tower at a university to make way for a new high-efficiency tower and filtration system. The...
Danger sign for rigging, dismantling & demolition site
Rigging, Dismantling & Demolition Project Safety

Safety is the number one priority on every R. Baker & Son project, from dismantling, rigging, and demolition, to plant decommissioning, plant relocation, and environmental services. Safeguards...
construction worker performing a multi heat exchanger changeout 
Baker Performs Multi Heat Exchanger Changeout

Back in early 2021, R. Baker & Son took part in a food manufacturing construction project in which we performed rigging and assembly of six large, high-pressure steam ovens over a ten-week...
Pre-construction, tablet on table of demolition contractor.
Preconstruction Services

The goal on every construction, renovation or demolition project is to have experienced, reputable contractors bid the project competitively. Preconstruction services, often referred to as precon,...
Asset Recovery: Refurbished Parts and Equipment in High Demand
Asset Recovery: Refurbished Parts and Equipment in High Demand

With supply chain shortages and inflation continuing into 2022, the demand for reconditioned parts and equipment is on the rise. Investment recovery, also known as asset recovery, of aged equipment...
Generator Replacement
Weekend Standby Generator Replacement

A large laboratory and office complex needed to replace an existing standby generator with a new, larger 2000 kW unit with associated automatic transfer switches and day tank. The owner needed the...
Rigging Project - Mechanical Room and Equipment
R. Baker & Son: Rigging Project Consultation

A longtime R. Baker & Son client approached us to help out on a very large project that was being proposed by one of the construction company’s satellite offices in Virginia. The project...
Interior Demolition: Epoxy Floor Removal Project
Interior Demolition: Epoxy Floor Removal

R. Baker & Son was contracted to perform interior demolition at a New Jersey pharmaceuticals manufacturing plant. Originally built in 1948, the second floor of the two-story building had served...