All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Demolition of Uranium Facility, Once the Largest Building in U.S.

Demolition of Uranium Facility, Once the Largest Building in U.S.

When the K-25 uranium enrichment facility was built in the mid-1940s as part of the Manhattan Project in Oak Ridge, Tennessee, it was the world’s largest building under one roof. Seventy years later, demolition of the enormous forty-four acre building was completed after a five-year project.

K-25 was commissioned by the U.S. government during World War II as part of the top-secret race to build the world’s first atomic bomb. Within the walls of the half-mile-long, 2 million square foot U-shaped facility, 12,000 workers produced, via gaseous diffusion, the enriched uranium that was used in atomic bombs dropped on Japan in 1945. Following the war, K-25 remained in operation producing enriched uranium for defense and commercial purposes until it was shut down in 1964. Other buildings at the Oak Ridge facility continued producing uranium until 1987.

Though demolition contractors began taking down the K-25 building in 2008, the complex project was ten years in the making. Due to the hazardous nature of the uranium operation, extensive preparation and remediation were required before demolition could commence. Among numerous Radioactive sludge was removed from a series of underground gunite tanks in 1999, and an onsite waste processing facility was built in 2003 to accept contaminated waste generated during site cleanup. Depleted uranium cylinders were shipped, more than 47,000 tons of metal was removed, several other buildings were demolished, and roads were constructed to accommodate vehicles removing project debris.

Demolition of K-25 was slated to last six years, from 2008 to 2014, but demolition contractors were able to complete the project one year ahead of schedule and approximately $300 million under its original $2.2 billion budget.

R. Baker & Son - All Industrial Services
1 Globe Court
Red Bank, NJ 07701
Phone: 732-222-3553
Web: http://www.rbaker.com

Full News Archive

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

construction worker performing a multi heat exchanger changeout 
Baker Performs Multi Heat Exchanger Changeout

Back in early 2021, R. Baker & Son took part in a food manufacturing construction project in which we performed rigging and assembly of six large, high-pressure steam ovens over a ten-week...
Pre-construction, tablet on table of demolition contractor.
Preconstruction Services

The goal on every construction, renovation or demolition project is to have experienced, reputable contractors bid the project competitively. Preconstruction services, often referred to as precon,...
Asset Recovery: Refurbished Parts and Equipment in High Demand
Asset Recovery: Refurbished Parts and Equipment in High Demand

With supply chain shortages and inflation continuing into 2022, the demand for reconditioned parts and equipment is on the rise. Investment recovery, also known as asset recovery, of aged equipment...
Generator Replacement
Weekend Standby Generator Replacement

A large laboratory and office complex needed to replace an existing standby generator with a new, larger 2000 kW unit with associated automatic transfer switches and day tank. The owner needed the...
Rigging Project - Mechanical Room and Equipment
R. Baker & Son: Rigging Project Consultation

A longtime R. Baker & Son client approached us to help out on a very large project that was being proposed by one of the construction company’s satellite offices in Virginia. The project...
Interior Demolition: Epoxy Floor Removal Project
Interior Demolition: Epoxy Floor Removal

R. Baker & Son was contracted to perform interior demolition at a New Jersey pharmaceuticals manufacturing plant. Originally built in 1948, the second floor of the two-story building had served...
Plant Demolition Project - Safety - Process Equipment
Pilot Plant Demolition Project

During a plant consolidation project, a three-story, 39,000 sq. ft. chemical pilot plant required demolition to make way for a future Butler storage building. R. Baker & Son worked closely with...
Decommissioning & Dismantling of HVAC Equipment - Pharma
Decommissioning and Dismantling of HVAC Equipment - Pharma

A 55,000 sq. ft. pharmaceutical facility in New Jersey was slated to undergo demolition. The 60-year-old building had undergone previous renovations over the years during which obsolete HVAC...