All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Demolition of Uranium Facility, Once the Largest Building in U.S.

Demolition of Uranium Facility, Once the Largest Building in U.S.

When the K-25 uranium enrichment facility was built in the mid-1940s as part of the Manhattan Project in Oak Ridge, Tennessee, it was the world’s largest building under one roof. Seventy years later, demolition of the enormous forty-four acre building was completed after a five-year project.

K-25 was commissioned by the U.S. government during World War II as part of the top-secret race to build the world’s first atomic bomb. Within the walls of the half-mile-long, 2 million square foot U-shaped facility, 12,000 workers produced, via gaseous diffusion, the enriched uranium that was used in atomic bombs dropped on Japan in 1945. Following the war, K-25 remained in operation producing enriched uranium for defense and commercial purposes until it was shut down in 1964. Other buildings at the Oak Ridge facility continued producing uranium until 1987.

Though demolition contractors began taking down the K-25 building in 2008, the complex project was ten years in the making. Due to the hazardous nature of the uranium operation, extensive preparation and remediation were required before demolition could commence. Among numerous Radioactive sludge was removed from a series of underground gunite tanks in 1999, and an onsite waste processing facility was built in 2003 to accept contaminated waste generated during site cleanup. Depleted uranium cylinders were shipped, more than 47,000 tons of metal was removed, several other buildings were demolished, and roads were constructed to accommodate vehicles removing project debris.

Demolition of K-25 was slated to last six years, from 2008 to 2014, but demolition contractors were able to complete the project one year ahead of schedule and approximately $300 million under its original $2.2 billion budget.

R. Baker & Son - All Industrial Services
1 Globe Court
Red Bank, NJ 07701
Phone: 732-222-3553
Web: http://www.rbaker.com

Full News Archive

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Rigging - Process Equipment
Rigging and Setting the Final Pieces of Process Equipment

A large, ongoing pharmaceutical project was facing a dilemma. With most work progressing smoothly and on-schedule, equipment for one very important process area would not be arriving onsite until the...
Interior Demolition Contractor in the North East
Quick Mobilization on Interior Demolition Project

Late last spring, construction was about to get underway on a large new warehouse in upstate New York when the construction management firm called R. Baker & Son with an urgent request. The...
interior demolition, mechanical contractor, installing prefabricated skids
Rigging Prefab in Sequence

At the completion of the interior demolition phase of a large renovation project, the mechanical contractor approached R. Baker & Son to request their assistance with rigging and installing...
Green Roof Installation - R. Baker & Son Environmental Services
Rigging Team Assists in Green Roof Installation

After a new office building construction project in western-central New Jersey where R. Baker & Son had been rigging architectural features in the expansive atrium, the construction manager asked...
Demolition Day T-Shirt, R. Baker Demolition
Everyone Loves Demolition Day!

Back in the mid-1940s, the demolition wrecking ball was a unique new demolition tool. A massive heavy steel ball swung by a very skillful operator in a large crane. By carefully moving the crane and...
Logistics are vital to plant relocation project
Successful Plant Relocation

Relocating a plant is a highly demanding task, but a large portion of the work happens in the planning.Plant relocation projects must be handled through a master plan with multiple phases and...
R. Baker & Son All Industrial Services Warehouse
Storing and Rigging Specialized Bio-Equipment for New Laboratory

A biomedical research firm in upstate New York reached out to R. Baker & Son for assistance with a special project. Two areas of a 40,000 square foot research building were to be phased out to...
Abandoned Industrial Building Demolition
Reuse & Value Engineering

R. Baker & Son has nearly 85 years of experience helping customers save money on projects. One approach is to reuse existing building equipment, materials, furnishings, and architectural...