All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Substantial Cost Savings in Space Repurposing Project

Demolition contractor doing environmental cleanup

R. Baker & Son was contracted by a long time customer with an order to perform demolition, dismantling and equipment relocation work at an old production facility that was to be repurposed. Production rooms and corridors occupied the ground floor of the two-story building and a mechanical and electrical penthouse were on the second floor.

With safety as our first priority, Phase One of the project required the dismantling and removal of all air handlers, exhaust fans, heat exchangers, pumps, piping and motor control centers. Next, Baker removed concrete housekeeping pads and miscellaneous steel throughout the building. All MEP equipment was removed using two heavy duty Lull 1044Cs and a JLG 5394RT and moved to rigging and staging areas for further dismantling, separation of materials, and recycling.  The facility’s maintenance department worked closely with the Baker team to identify and salvage existing pumps and parts for reuse in other buildings or for attic stock. 

Phase Two of the project required an 80-ton crane to safely remove roof exhaust fans, condensers, package AHUs, piping and ductwork. The third phase entailed the removal of several large pieces of process equipment and other machinery that was separated and match marked for use at another facility, including two lyophilizers, a large fluid bed and granulator, several isolators and glove boxes, as well as large in-floor scales and several 5,000 gallon process tanks.  Walls and ceilings were successfully removed while identifying and preserving recently-installed fiber optic inner ducts during demolition and dismantling. Floor demolition was more challenging and time consuming, requiring removal of thick, sloped epoxy floors with pneumatic hammers and scrapers. Facility restrooms, still in good shape, were left intact as a value engineering cost-savings item. 

Exterior blockwork was thoroughly cleaned, pointed and power washed using several articulating booms. As a cost saving measure, windows were cleaned and re-caulked for reuse. Where required, floors on both levels were flash-patched. R. Baker & Son had zero safety incidents on the project while adhering to an aggressive schedule and providing $260,000 in cost savings. 

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services, a  Service-Disabled Veteran-Owned Business (SDVOB)  in business since 1935, is a premier specialized contractor operating in the United States, Canada and Puerto Rico, with over one hundred employees and an exemplary safety record (we have been directly involved in four sites that received VPP OSHA Safety Awards). R. Baker & Son is financially strong, with bonding capabilities over $10 million. Capabilities include industrial and commercial demolition, rigging, machinery- and plant-moving, dismantling, decommissioning, plant and equipment relocation, interior demolition, selective demolition, warehousing, wrecking and razing, millwright, plant reconfigurations, heavy rigging, salvage, environmental services, remediation, decontamination, abatement, and investment and asset recovery.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553
http://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

construction worker performing a multi heat exchanger changeout 
Baker Performs Multi Heat Exchanger Changeout

Back in early 2021, R. Baker & Son took part in a food manufacturing construction project in which we performed rigging and assembly of six large, high-pressure steam ovens over a ten-week...
Pre-construction, tablet on table of demolition contractor.
Preconstruction Services

The goal on every construction, renovation or demolition project is to have experienced, reputable contractors bid the project competitively. Preconstruction services, often referred to as precon,...
Asset Recovery: Refurbished Parts and Equipment in High Demand
Asset Recovery: Refurbished Parts and Equipment in High Demand

With supply chain shortages and inflation continuing into 2022, the demand for reconditioned parts and equipment is on the rise. Investment recovery, also known as asset recovery, of aged equipment...
Generator Replacement
Weekend Standby Generator Replacement

A large laboratory and office complex needed to replace an existing standby generator with a new, larger 2000 kW unit with associated automatic transfer switches and day tank. The owner needed the...
Rigging Project - Mechanical Room and Equipment
R. Baker & Son: Rigging Project Consultation

A longtime R. Baker & Son client approached us to help out on a very large project that was being proposed by one of the construction company’s satellite offices in Virginia. The project...
Interior Demolition: Epoxy Floor Removal Project
Interior Demolition: Epoxy Floor Removal

R. Baker & Son was contracted to perform interior demolition at a New Jersey pharmaceuticals manufacturing plant. Originally built in 1948, the second floor of the two-story building had served...
Plant Demolition Project - Safety - Process Equipment
Pilot Plant Demolition Project

During a plant consolidation project, a three-story, 39,000 sq. ft. chemical pilot plant required demolition to make way for a future Butler storage building. R. Baker & Son worked closely with...
Decommissioning & Dismantling of HVAC Equipment - Pharma
Decommissioning and Dismantling of HVAC Equipment - Pharma

A 55,000 sq. ft. pharmaceutical facility in New Jersey was slated to undergo demolition. The 60-year-old building had undergone previous renovations over the years during which obsolete HVAC...