All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Industrial Rigging A Wind Turbine

Industrial Rigging A Wind Turbine

For those of us who work at R. Baker & Son, industrial rigging and demolition is a way of life. Imagine the surprise when, on a trip a few years ago to visit family, an R. Baker staff member found himself watching the assembly of a giant wind turbine just a stone’s throw from his uncle’s home in upstate New York. Family members had seen several large tractor trailers transporting enormous conical steel tower sections and fiberglass blades through town, so they decided to visit the nearby wind farm under construction at the top of a mountain. There they watched crews rig and place a tower section and spoke with the industrial rigging contractors charged with erecting the wind turbines. 

A 500-ton high-lift crawler crane and a 100-ton hydraulic crane were strategically positioned at the steel-reinforced concrete tower base. Riggers connected each end of tower section to each crane, and the section was lifted from the oversize tractor trailer, which had somehow negotiated its way over winding roads to the mountaintop. The smaller crane steadied the section as the high-lift crane rigged it into a vertical position.  The section was then carefully rigged onto numerous steel bolts the top of the two sections of tower already in place. The industrial rigging company foreman explained that the rigging of the 40-ton nacelle, the housing for the generator and other main components, would follow once the top tower section had been properly secured. The rotor, assembled onsite with its three 120-ft. blades, would then be rigged in one piece and connected to the nacelle.  Once completed, the wind farm would have a generating capacity of over one hundred megawatts. 

R. Baker & Son - All Industrial Services
1 Globe Court
Red Bank, NJ 07701
732-222-3553

http://www/rbaker.com


 

Full News Archive

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

construction worker performing a multi heat exchanger changeout 
Baker Performs Multi Heat Exchanger Changeout

Back in early 2021, R. Baker & Son took part in a food manufacturing construction project in which we performed rigging and assembly of six large, high-pressure steam ovens over a ten-week...
Pre-construction, tablet on table of demolition contractor.
Preconstruction Services

The goal on every construction, renovation or demolition project is to have experienced, reputable contractors bid the project competitively. Preconstruction services, often referred to as precon,...
Asset Recovery: Refurbished Parts and Equipment in High Demand
Asset Recovery: Refurbished Parts and Equipment in High Demand

With supply chain shortages and inflation continuing into 2022, the demand for reconditioned parts and equipment is on the rise. Investment recovery, also known as asset recovery, of aged equipment...
Generator Replacement
Weekend Standby Generator Replacement

A large laboratory and office complex needed to replace an existing standby generator with a new, larger 2000 kW unit with associated automatic transfer switches and day tank. The owner needed the...
Rigging Project - Mechanical Room and Equipment
R. Baker & Son: Rigging Project Consultation

A longtime R. Baker & Son client approached us to help out on a very large project that was being proposed by one of the construction company’s satellite offices in Virginia. The project...
Interior Demolition: Epoxy Floor Removal Project
Interior Demolition: Epoxy Floor Removal

R. Baker & Son was contracted to perform interior demolition at a New Jersey pharmaceuticals manufacturing plant. Originally built in 1948, the second floor of the two-story building had served...
Plant Demolition Project - Safety - Process Equipment
Pilot Plant Demolition Project

During a plant consolidation project, a three-story, 39,000 sq. ft. chemical pilot plant required demolition to make way for a future Butler storage building. R. Baker & Son worked closely with...
Decommissioning & Dismantling of HVAC Equipment - Pharma
Decommissioning and Dismantling of HVAC Equipment - Pharma

A 55,000 sq. ft. pharmaceutical facility in New Jersey was slated to undergo demolition. The 60-year-old building had undergone previous renovations over the years during which obsolete HVAC...