All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Interior Demolition: Epoxy Floor Removal

Interior Demolition: Epoxy Floor Removal Project

R. Baker & Son was contracted to perform interior demolition at a New Jersey pharmaceuticals manufacturing plant. Originally built in 1948, the second floor of the two-story building had served for decades as a 62-room vivarium, and the now-vacant area was to be repurposed as open offices with high ceilings and laboratories with downflow booths.
 
The first demolition task required to prepare for renovation was the removal of all of the old terracotta block and concrete walls throughout the 25,500 sq. ft. area. Removal of the walls revealed sixty-two individual 12’ x 12’ areas with thick, pitched, troweled-on epoxy floors with drains in the center of the rooms, as well as seven corridors. Removal of the epoxy floors down to the concrete below would require multiple passes by five Blastrac BMS-280 ride-on floor scrapers. Four National 550 floor scrapers were utilized in areas that couldn’t be accessed by the ride-on machines. Other equipment used during the wall and floor demolition included three Bobcats and two pneumatic hammers.
 
Following wall demolition, all drains were plugged and filled with non-shrink concrete. Once the epoxy floors were removed down to the concrete base, R. Baker & Son brought in a BIM scanner system contractor to determine the level of the floors within +/- 1/32” as they needed to be as level as possible, with no high or low points. The BIM contractor identified about a dozen areas that needed to come down in height in order to have a 2-inch total poured concrete floor. Baker crew members prepped and patched several low areas with non-shrink grout to make them level. BIM scans were repeated several times until all high and low points were brought to level. 

The floor was now ready for a new poured resinous surface. Prior to the pour, R. Baker & Son was asked to assist with identifying and filling any open floor areas where conduit and piping had passed through to create a complete seal for the new resinous system. Finally, the entire area was broom swept, cleaned, and vacuumed. The entire floor demolition and preparation project was performed safely to our site-specific safety plan and took approximately three weeks to complete, clearing the way for the next project phase to begin.

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services, a Minority and Women-Owned Business Enterprise (M/WBE), in business since 1935, is a premier specialized contractor operating in the United States, Canada, and Puerto Rico, with over one hundred employees and an exemplary safety record (we have been directly involved in four sites that received VPP OSHA Safety Awards). R. Baker & Son is financially strong, with bonding capabilities of over $10 million. Capabilities include industrial and commercial demolition, rigging, machinery- and plant-moving, dismantling, decommissioning, plant and equipment relocation, interior demolition, selective demolition, warehousing, wrecking and razing, millwright, plant reconfigurations, heavy rigging, salvage, environmental services, remediation, decontamination, abatement, and investment and asset recovery.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553

https://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

R. Baker Industrial Worker With Laptop At Demolition Project
Precision Planning in Construction Demolition

When it comes to defining a construction project's approach, most proficient project management teams can produce a plan that methodically lays out phases, tasks, and timelines in meticulous...
interior demolition at a manufacturing and production facility, rigging crew
Precision MEP Install at a South Jersey Manufacturing Facility

As part of a 150,000 sq/ft manufacturing and production facility renovation project in South Jersey, R Baker had completed the selective interior demolition work months before. This work included...
Precision Demolition Equipment
Precision Demolition: R. Baker & Son's Advanced Equipment & Techniques

When tackling the complexities of industrial demolition, you're not just swinging a wrecking ball. At R. Baker & Son, we understand that precision, safety, and efficiency are paramount....
R. Baker & Son Crane used in plant relocation
Comprehensive Guide to Plant Relocation: Planning for Success

Strategic Planning: The Foundation of Plant Relocation Plant relocation represents a complex logistical challenge where success hinges primarily on thorough planning. A comprehensive master plan...
How Virtual Reality is Changing Riggers Training
How Virtual Reality is Changing Riggers Training

Using virtual reality (VR) in training for rigging professionals offers a multitude of benefits that enhance the learning experience and improve safety and efficiency in the field. Here are some key...
Chemical Bursting: Concrete Demolition
Chemical Bursting: The Silent Revolution in Concrete Demolition

While traditional concrete demolition often relies on hydraulic breakers, pneumatic drills, saw cutting, and explosives, some projects demand more subtle approaches. Chemical bursting, also known as...
Demolition and Rigging: A Half Century of Safety Innovation
Demolition and Rigging: A Half Century of Safety Innovation

Safety stands as the cornerstone of everything we do at R Baker and Son's demolition and rigging operations. Those of us with decades of experience in the field understand the importance of...
Toolbox Talks, R. Baker & Son Demolition Crew
Safety Through Dialogue: The Critical Role of Toolbox Talks

Toolbox talks are a cornerstone of effective company safety programs. These informal safety meetings, typically held on job sites before work begins, focus on specific safety topics and are designed...