All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Data Center Rigging & MEP Installation: Keeping Projects on Schedule

R. Baker & Son riggers setting water-cooled centrifugal chillers for data center cooling availability.

Safe, efficient rigging and assembly of data center MEP systems starts with understanding how a data center operates. That means knowing what mechanical and electrical equipment is required, how each piece needs to be routed into place, and in what sequence. At R. Baker & Son, we work alongside electrical contractors on power distribution systems, mechanical contractors on cooling systems, and IT contractors throughout the build.

Permanent Power Comes First
A recent data center project is a perfect example. The schedule was aggressive and built around specific milestones, with permanent power as the first and most critical. Working closely with the electrical contractor, our team received and rigged in two 2500kva 4000 amp double-ended substations. Each substation included two 35kv medium voltage switches on each end, two large transformers, and the 480v low voltage distribution gear in between.

Next, R. Baker installed several large automatic transfer switches (ATS), along with two 2 MW generators and their associated paralleling gear.

Meeting the Cooling Availability Date
On the mechanical side, the goal was to have equipment ready in time for the facility's cooling availability date. That meant bringing in several 1,200-ton water-cooled centrifugal chillers, two heat pump chillers, two large cooling towers, and several plate and frame heat exchangers.

The cooling towers required dunnage to be installed before they could be set in place and assembled, so R. Baker assigned a separate team to handle this sizable scope. Completing that work allowed the mechanical contractor to finish installing the 10-inch condenser water piping, makeup water, and filtration systems.

Installing CRAC and CRAH Units
With nearly all major equipment set and assembled, our mechanical rigging crew moved on to installing several computer room air conditioning (CRAC) units for hot aisle and cold aisle cooling, along with four large 40,000 CFM computer room air handling (CRAH) units.

Collaboration That Kept the Project Moving
By working closely with the mechanical and electrical contractors, R. Baker helped ensure electrical and piping terminations began on time, supporting the overall data center project schedule. One especially valuable part of that collaboration was a combined daily toolbox talk. Every morning at 7 a.m., R. Baker and the other trades met together, which built a strong bond between crews and kept everyone aligned on safety and the day's priorities.

Planning a data center project? Contact R. Baker & Son to learn how our rigging team can help you hit every milestone.

Founded in 1935, R. Baker & Son All Industrial Services is a certified Minority and Women-Owned Business Enterprise (M/WBE) - recognized as the oldest and largest M/WBE-certified demolition contractor in North America. We are your trusted partner for complex industrial and construction projects, specializing in heavy rigging, machinery moving, plant relocation, and expert crane erection, dismantling, and support services across the United States, Canada, and Puerto Rico.

With significant bonding capacity and an unmatched safety record backed by extensive involvement in OSHA VPP Star projects, we deliver precision and reliability to every job site. Our comprehensive services include heavy rigging, complex machinery installation and removal, plant relocation, industrial dismantling, and specialized support for high-reach and tower crane operations.

Discover why leading industrial and commercial clients rely on R. Baker & Son for safe, precise solutions to their most demanding heavy rigging and dismantling projects. Learn more about our expertise in data center rigging.

Full News Archive

2026

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

R. Baker & Son riggers setting water-cooled centrifugal chillers for data center cooling availability.
Data Center Rigging & MEP Installation: Keeping Projects on Schedule

Safe, efficient rigging and assembly of data center MEP systems starts with understanding how a data center operates. That means knowing what mechanical and electrical equipment is required, how each...
An 80-ton crane hoisting a new MRI machine during a medical equipment replacement project
Swapping an 8-Ton MRI in 48 Hours: Inside a Complex Medical Rigging Project

Six months after rigging two MRI machines, a CT scanner, a PET scanner, and their associated chillers and cooling equipment into a brand-new medical treatment facility, we got another call from the...
Precision Chiller Dismantling & Mechanical Retrofit Case Study
Precision Chiller Dismantling & Mechanical Retrofit Case Study

A local New Jersey representative for a major chiller manufacturer recommended R. Baker & Son for a demanding chiller change-out project. The scope: remove two 1,200-ton chillers and their...
Discover how a custom negative pressure wall and real-time monitoring protected a pharmaceutical cleanroom during high-stakes facility demolition.
How to Protect Active Cleanrooms During Demolition: A Negative Pressure Wall Case Study

Protecting a client's environment during demolition and renovation work has always been part of what we do at R. Baker & Son. Anyone in the industry knows ICRA protection, the barrier system...
rigging medical equipment into a hospital - R. Baker & Son
Just-in-Time Rigging Keeps a Hospital Running During a Critical Enabling Project

R. Baker & Son received a call from a concerned South Jersey mechanical contractor facing a complex rigging project on a tight deadline. Another rigging contractor had passed on the job late in...
Riggers assembling tower crane sections during construction - R. Baker & Son - Master Riggers.
How Mobile and Tower Cranes Are Assembled & Dismantled

Mobile cranes come in many styles, shapes, and sizes, with the hydraulic crane and the luffing jib being the most common. R. Baker & Son has worked with just about every mobile crane on the...
Demolition concrete debris fed into an industrial crusher for recycling
7 Ways Demolition Protects Communities & the Planet

7 Ways Demolition Builds Better Communities -And Why It Matters When most people picture demolition, they see dust clouds and falling walls. What they don't see is the careful planning,...
R. Baker & Son industrial contractors executing mission-critical transformer replacement with rigging equipment at medical facility
How R. Baker & Son Executes High-Stakes Projects with Engineered Work Plans

Mission-critical and high-stakes projects demand detailed, preplanned coordination to ensure success at every level. When it comes to plant shutdowns, startups, repairs, changeovers, and equipment...