Demo Project Bid Leveling Sheets: What is Included and Excluded Can Make All the

Demo Project Bid Leveling Sheets: What is Included and Excluded Can Make All the

One of the keys to a successful demolition or selective demolition project outcome is the development and use of a checklist during the bidding process known as the leveling sheet. The leveling sheet defines the scope of the project in minute detail, spelling out exactly what is included or excluded in each demolition contractor’s proposal and effectively leveling the bids for a fair comparison. Without a leveling sheet, items can go unidentified, leading to an array of problems, change orders, delays, finger-pointing, and all-around hard feelings between client and contractor.

Leveling sheet specifications on a demolition project might include:

Will demolition equipment used be battery operated or diesel?

Environmental hazards such as asbestos, lead paint, or old tanks – will they be remediated, and how?

Is the project union or non-union, and what are the working hours? Will there be second and third shifts?

Will dust and vibration be limited to specific hours?

Asset recovery – are there items of value such as copper wire or salvageable equipment that can offset project costs?

Will the demolition contractor use subcontractors to perform electrical, plumbing or mechanical aspects of their project?

Does the demolition project include specific safety items such as ISNetworld, VPPP, HAZWOPER, etc.?

Using a leveling sheet to identify what is included or excluded on any demolition or select demolition project can ensure that equipment and services are purchased wholesale from the outset, not at retail prices after the fact. Doing your homework can save a lot of money and streamline your demolition project.

R. Baker & Son - All Industrial Service
1 Globe Court
Red Bank, NJ 07701
http://www.rbaker.com

Full News Archive

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Preventing, Recognizing, and Treating Heat Related Illness
R. Baker Workers Trained In Heat Related Illness

With summer only just begun, there are likely many hot days ahead. In construction, demolition, and rigging, heat-related illness is a very real threat if the proper steps are not taken to prevent...
Tank Rigging Project - All Industrial Services
Tank Rigging Project

A large food processing plant was referred to R. Baker & Son to take on the task of rigging all new equipment into an existing 200,000 sq. ft. facility. The majority of equipment consisted of...
Skid Steer Loader - Demolition Contractor
The Skid Steer Loader, Workhorse of the Demolition Industry

One of the most versatile machines on any construction or demolition project is the skid steer loader, a compact, rigid-framed, engine-powered machine with lift arms that can be fitted with a variety...
Rigging Tanks In Pharmaceutical Plant
Baker Handles Pharma Rigging Project with TLC

R. Baker & Son was challenged with a unique rigging project for a pharmaceutical client in northern New Jersey.The scope of work called for removal of numerous pieces of process equipment...
Clean Air, Demolition Project
Innovative Approach to Clean Air on Demo Project

A good demolition plan often takes a holistic approach to achieve common project goals. The return on investment is almost always well worth it. R. Baker & Son was challenged to perform a...
Demolition Project - Radio Communication in Construction
Proper Radio Communication on Construction Sites

Communication is key, is a popular saying that is especially fitting on a construction, rigging, or demolition job-site. Radio communication is an important tool that helps team members work more...
Demolition, Selective Demolition, Interior Demolition
Demolition and Closing the Gap

Oftentimes during selective demolition or interior demolition activities, opening up walls, ceilings, floors, shafts and pits can expose a plethora of structural problems, code issues, and other...
Rigging - Process Equipment
Rigging and Setting the Final Pieces of Process Equipment

A large, ongoing pharmaceutical project was facing a dilemma. With most work progressing smoothly and on-schedule, equipment for one very important process area would not be arriving onsite until the...