All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Rigging Process Equipment Narrow Shaft

Rigging Process Equipment Narrow Shaft

An old R&D facility in Northern New Jersey needed to renovate an area to make way for an important new expansion. Because real estate for needed process equipment was limited, the only area available was interstitial space located one floor below, but the equipment would need to be rigged into the space through an existing 8’ x 8’ x 17’ utility shaft congested with piping. The project team challenged R. Baker & Son and the mechanical contractor to put their heads together and come up with a plan. 

Equipment that would need to be rigged through the narrow shaft included an osmosis system, a clean steam generator, condensate tanks, pumps, and heat exchangers, as well as several motor control centers, small air handling units, and fan coil units. Since removing all of the conduit and piping was not feasible, the Baker rigging team and the mechanical contractor determined that two 6-inch chilled water lines and two 4-inch hot water reheat lines, along with about a dozen electrical and control lines, would need to be removed in order to clear enough vertical space to rig the equipment to the area below. Much of the equipment was shipped in sections that would be rigged down the narrow shaft and assembled in the interstitial space. 

Two I-beams were installed at the top of the shaft, and 1.5-ton chain hoists were connected to each. Using block-and-tackle, slings, and a spreader bar, the Baker rigging team carefully lowered each piece through the maze of remaining piping and supports using tag lines, often with only an inch or two of room to spare. Once at the bottom, each piece of equipment was set on skates, rolled to its predetermined location as indicated on the BIM model, assembled, and connected under the supervision of a vendor representative. Chilled water, hot water, and electrical lines were reinstalled in the shaft to bring existing systems back online. The entire project was successfully executed between Christmas and New Year’s Day, when the facility had minimal operations.

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services, a  Service-Disabled Veteran-Owned Business (SDVOB)  in business since 1935, is a premier specialized contractor operating in the United States, Canada and Puerto Rico, with over one hundred employees and an exemplary safety record (we have been directly involved in four sites that received VPP OSHA Safety Awards). R. Baker & Son is financially strong, with bonding capabilities over $10 million. Capabilities include industrial and commercial demolition, rigging, machinery- and plant-moving, dismantling, decommissioning, plant and equipment relocation, interior demolition, selective demolition, warehousing, wrecking and razing, millwright, plant reconfigurations, heavy rigging, salvage, environmental services, remediation, decontamination, abatement, and investment and asset recovery.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553

http://rbaker.com/

Full News Archive

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

rigging project planning, man welding steel beams
Expert Rigging: Meticulous Planning for Safe Lift Projects

A major rigging project demands meticulous planning and execution. While the actual lift may only span a day or two, it represents the culmination of weeks or even months of intense...
Rigging Equipment, skyline NYC, Women Owned Business
Efficient Rigging and Equipment Setup: Planning and Collaboration

R. Baker & Son was contacted by a large mechanical contractor with whom we have worked in the past and who works in the New Jersey-Philadelphia area. They had a large renovation project that...
Environmental Solutions for Dismantling, Decommissioning and Demolition
Eco-Friendly Solutions for Dismantling, Demo & Decommissioning

Demolition, dismantling, or decommissioning of industrial facilities is a complex process that requires meticulous planning and execution. These sites often contain hazardous chemicals, substances,...
Selective Demolition and Rigging at Process Plant
Selective Demolition and Rigging at Process Plant

R. Baker & Son recently performed selective demolition and equipment rigging for a process plant construction project. The selective demolition was necessary to prepare the existing facility to...
Chiller and Cooling Tower Installation at a South Jersey Hospital
Rigging Success: Chiller & Cooling Tower Installation at Jersey Hospital

Recently, R. Baker & Son team was faced with the task of installing a new 1200-ton chiller and double cell cooling tower at a South Jersey hospital. The project was referred to us by a trusted...
Industrial Workers Rigging 2024
Celebrating a New Year from R. Baker & Son

As a new year begins, we reflect on our deep appreciation for all our employees, associates, contractors, vendors, and customers. Our founder, Ruby Baker, started R. Baker & Son in 1935 during...
Define Demolition Scope and Budget
Maximizing Your Demolition Project - Tips to Define Scope|Budget

Often on large construction and renovation projects, the demolition portion of the Scope of Work is vague or poorly defined. It’s not uncommon to see a boxed-out area on drawings with only a...
Demolition in New York,
Industrial Demolition in NYC: A Look at the Process and Impact

When it comes to industrial demolition in NYC, R. Baker & Son has been trusted for well over 80years. With their expertise, experience, and commitment to safety, they have become one of the most...