All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Substation & Mechanical Selective Demolition: Out With the Old

Substation and Mechanical Selective Demolition

A new pharmaceutical company took over an existing North Jersey facility with plans for major demolition and renovation. Design work began immediately, and long-lead equipment was ordered early on. To meet the aggressive schedule, a parallel selective demolition plan was developed by R. Baker & Son in anticipation of the arrival of the new equipment. 

Plans called for a new, larger electrical service requiring removal of an existing substation and installation of a new one. Two existing 600 HP boilers were slated for removal to make way for eight smaller high-efficiency boilers. Four 75-ton chillers, only five years old, were to remain, but aged 100% outside air handlers and associated piping were to be replaced by new recirculating units and required demolition. Because the facility was to be operational for the duration of the project, however, it was necessary for utilities and HVAC systems remain in place until new equipment arrived, at which point R. Baker & Son’s portion of the project would need to move forward swiftly. This required a close team effort between the Baker team, electrical and mechanical contractors, and the owner.  

The first, and most critical, swap-out was the removal of a 1500 kVA single-ended substation and installation of a 2500 kVA double-ended substation on a newly-enlarged concrete pad. After weeks of planning and preparation, the electrical shutdown began on a Friday night.  Following all lockout-tagout procedures, the equipment removal proceeded through the weekend. The new substation was rigged in place on Monday morning, and reconnection began immediately, with a one-week timeframe to get the power back on. 

Over the next several consecutive Fridays, R. Baker & Son removed the two existing boilers so the eight smaller boilers could be rigged, set, installed in place, and readied for piping. Finally, the air handlers were removed in a set sequence to keep the cooling system running while the new units were installed.  The Baker team performed asset recovery of the boilers and substations for resale allowed the owner to recoup their value and reduce the overall cost of the project.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553
http://rbaker.com/selective-demolition.php

Full News Archive

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Carne and Rigging Simulation, Virtual Reality
Virtual Reality The Future of Crane & Rigging Training?

Industrial Training International or ITI has 9 training centers in North America with a virtual reality (VR) crane simulator for authentic rigging training and assessment. ITI VR Mobile Crane...
Rigging & Construction Careers
Rigging, Hoisting & Heavy Equipment Careers

The “skills gap” debate runs deep with a lot of people in this country and although the argument isn’t new, it’s still vigorously debated. Mike Rowe from the hit TV show...
Demolition contractor doing environmental cleanup
Substantial Cost Savings in Space Repurposing Project

R. Baker & Son was contracted by a long time customer with an order to perform demolition, dismantling and equipment relocation work at an old production facility that was to be repurposed....
Demolition of a Utility Tunnel
Demolition: A Little Ingenuity Goes a Long Way

Over decades at a Central New Jersey facility, a long MEP utility tunnel was used to carry various plumbing, HVAC, electrical and control lines. When systems began to age and several plumbing lines...
Colossal Claw Revolutionizes Rigging of Sunken Oil Rigs in the Gulf of Mexico
Colossal Claw Revolutionizes Rigging of Sunken Oil Rigs

One of the most striking man-made sights in the Gulf of Mexico is the Versabar VB 10,000, the largest seagoing heavy lift vessel ever built in the United States. Based on Versabar’s smaller...
Kosciusko Bridge Demolition
Kosciusko Bridge Demolition UPDATE

Last March, R. Baker & Son wrote about the demolition of the old Kosciuszko Bridge, which at the time had been scheduled to take place during the summer of 2017. After a few delays, remaining...
56 Leonard Street
Innovative Plan in Manhattan High Rise Project

By the time construction of 56 Leonard, an iconic new residential skyscraper located in the Tribeca section of Manhattan, wrapped up late last year, all of its 145 luxury units had sold out, some...
industrial air shower and dust removal room
Cleanroom Demolition

Interior and selective demolition projects involving cleanrooms are particularly sensitive when it comes to controlling of particulates, temperature, humidity, and pressurization. R. Baker & Son...