All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Substation & Mechanical Selective Demolition: Out With the Old

Substation and Mechanical Selective Demolition

A new pharmaceutical company took over an existing North Jersey facility with plans for major demolition and renovation. Design work began immediately, and long-lead equipment was ordered early on. To meet the aggressive schedule, a parallel selective demolition plan was developed by R. Baker & Son in anticipation of the arrival of the new equipment. 

Plans called for a new, larger electrical service requiring removal of an existing substation and installation of a new one. Two existing 600 HP boilers were slated for removal to make way for eight smaller high-efficiency boilers. Four 75-ton chillers, only five years old, were to remain, but aged 100% outside air handlers and associated piping were to be replaced by new recirculating units and required demolition. Because the facility was to be operational for the duration of the project, however, it was necessary for utilities and HVAC systems remain in place until new equipment arrived, at which point R. Baker & Son’s portion of the project would need to move forward swiftly. This required a close team effort between the Baker team, electrical and mechanical contractors, and the owner.  

The first, and most critical, swap-out was the removal of a 1500 kVA single-ended substation and installation of a 2500 kVA double-ended substation on a newly-enlarged concrete pad. After weeks of planning and preparation, the electrical shutdown began on a Friday night.  Following all lockout-tagout procedures, the equipment removal proceeded through the weekend. The new substation was rigged in place on Monday morning, and reconnection began immediately, with a one-week timeframe to get the power back on. 

Over the next several consecutive Fridays, R. Baker & Son removed the two existing boilers so the eight smaller boilers could be rigged, set, installed in place, and readied for piping. Finally, the air handlers were removed in a set sequence to keep the cooling system running while the new units were installed.  The Baker team performed asset recovery of the boilers and substations for resale allowed the owner to recoup their value and reduce the overall cost of the project.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553
http://rbaker.com/selective-demolition.php

Full News Archive

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Demolition Project Goes Underground
Demolition Project Goes Underground

A 175,000 square-foot OTC R&D and production building, constructed in the early 1960s, was undergoing complete interior demolition to be repurposed as a pilot facility. The demolition schedule...
Copper Recycling Offsets Dismantling Project Costs
Copper Recycling Offsets Dismantling Project Costs

A large electrical-mechanical contractor hired R. Baker & Son to perform all of the electrical equipment dismantling and mechanical equipment removal at an old vitamin production facility...
CUP Multi-Phase Selective Demolition Project: Demo by Color
CUP Multi-Phase Selective Demolition Project: Demo by Color

An aging central utility plant serving a large northern New Jersey hospital was due for complete renovation, including the replacement of almost all equipment including boilers, chillers, cooling...
Rigging Safety Guidelines - Industrial Services
Rigging Safety Guidelines

Safety is paramount at R. Baker & Son, which is why we strictly observe all rigging safety regulations, guidelines and procedures on every lift we do. Guidelines for rigging safety: Inspect...
R. Baker Salvages Fixtures for Reuse on Plant Consolidation Project
R. Baker Salvages Fixtures for Reuse on Plant Consolidation

A longtime client approached R. Baker & Son with a plant relocation project in which operations at several partially-occupied buildings were to be moved to a single 200,000 sq. ft. building...
Planning for Rigging & Demo Projects
Safety Planning for Rigging and Demolition Projects

When performing a rigging or demolition project, falling materials, fall hazards, unstable structures, and a variety of other hazards can pose serious risks to both workers and the general public, so...
Rigging Process Equipment Narrow Shaft
Rigging Process Equipment Narrow Shaft

An old R&D facility in Northern New Jersey needed to renovate an area to make way for an important new expansion. Because real estate for needed process equipment was limited, the only area...
Demolition Equipment Maintenance
Demolition Equipment Maintenance SOP

Demolition equipment is always being put to the test. Every quality demolition contractor looks to get quality name equipment at a fair price. Demolition equipment maintenance falls under two...