All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Innovative Plan in Manhattan High Rise Project

56 Leonard Street

By the time construction of 56 Leonard, an iconic new residential skyscraper located in the Tribeca section of Manhattan, wrapped up late last year, all of its 145 luxury units had sold out, some going for prices as high as $48 million. Known as the Jenga Tower due to its stunning and unusual appearance, the glass-encased 60-story building features a staggered silhouette of shifting and varying floorplates, cantilevers, and balconies. Not surprisingly, construction of 56 Leonard was exceptionally complex, even by New York City standards, which was recognized last month when ENR New York named 56 Leonard 2017’s Best Project in the Residential/Hospitality category.  

R. Baker & Son took on one of the challenging project’s early hurdles: the removal of massive steel I-beams cantilevered 25 feet over the roof of an adjacent building. The falsework beams were installed on the 6th floor to provide temporary structural support until the concrete had sufficiently cured while construction progressed on the floors above. R. Baker & Son was challenged to develop an innovative plan to remove the huge beams safely and efficiently. Taking into account the many complex logistical challenges of the project, Baker engineers determined that beam sections would need to be cut and removed from the structure’s interior, rather from the exposed ends jutting from the building.  After hours of brainstorming, the Baker team came up with a unique and inventive solution that would provide the key to the project: custom-fabricated weighted dollies that would be used to slide the beams inward while serving as counterweights. 

The removal procedure began with Baker team members fabricating steel guides around each I-beam and securing them to nearby concrete columns. After attaching two heavily-weighted dollies to each beam, workers would cut a 4-foot section, each weighing 1,200 lbs., from the interior end of the I-beam. The dollies/counterweights prevented the cantilevered ends of the beams from tipping past the fulcrum point when the sections were detached. Each time a section was removed, Baker crew members used heavy-duty winches to wheel the remaining beam another four feet into the building. Then everything would be repositioned and the entire process would be repeated. The removed sections were stacked three high, and workers utilized an in-house material hoist to lower the 3,600-lb. stacks to ground level. 

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553http://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Interior Demolition - Wet Saw
Interior Demo: Mid-Project Changes Save Time and Money

Discovering an opportunity for substantial cost savings during a project in progress is always a welcome surprise, which was the case on a warehouse renovation in which R. Baker & Son was tasked...
Safety Plan, Demolition and Rigging Contractor
Site-Specific Safety Plan

A site-specific safety plan (SSSP) is an agreement that addresses project-specific safety concerns and challenges and how to manage them. It serves as a communication tool between involved...
Preventing, Recognizing, and Treating Heat Related Illness
R. Baker Workers Trained In Heat Related Illness

With summer only just begun, there are likely many hot days ahead. In construction, demolition, and rigging, heat-related illness is a very real threat if the proper steps are not taken to prevent...
Tank Rigging Project - All Industrial Services
Tank Rigging Project

A large food processing plant was referred to R. Baker & Son to take on the task of rigging all new equipment into an existing 200,000 sq. ft. facility. The majority of equipment consisted of...
Skid Steer Loader - Demolition Contractor
The Skid Steer Loader, Workhorse of the Demolition Industry

One of the most versatile machines on any construction or demolition project is the skid steer loader, a compact, rigid-framed, engine-powered machine with lift arms that can be fitted with a variety...
Rigging Tanks In Pharmaceutical Plant
Baker Handles Pharma Rigging Project with TLC

R. Baker & Son was challenged with a unique rigging project for a pharmaceutical client in northern New Jersey.The scope of work called for removal of numerous pieces of process equipment...
Clean Air, Demolition Project
Innovative Approach to Clean Air on Demo Project

A good demolition plan often takes a holistic approach to achieve common project goals. The return on investment is almost always well worth it. R. Baker & Son was challenged to perform a...
Demolition Project - Radio Communication in Construction
Proper Radio Communication on Construction Sites

Communication is key, is a popular saying that is especially fitting on a construction, rigging, or demolition job-site. Radio communication is an important tool that helps team members work more...