All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Innovative Plan in Manhattan High Rise Project

56 Leonard Street

By the time construction of 56 Leonard, an iconic new residential skyscraper located in the Tribeca section of Manhattan, wrapped up late last year, all of its 145 luxury units had sold out, some going for prices as high as $48 million. Known as the Jenga Tower due to its stunning and unusual appearance, the glass-encased 60-story building features a staggered silhouette of shifting and varying floorplates, cantilevers, and balconies. Not surprisingly, construction of 56 Leonard was exceptionally complex, even by New York City standards, which was recognized last month when ENR New York named 56 Leonard 2017’s Best Project in the Residential/Hospitality category.  

R. Baker & Son took on one of the challenging project’s early hurdles: the removal of massive steel I-beams cantilevered 25 feet over the roof of an adjacent building. The falsework beams were installed on the 6th floor to provide temporary structural support until the concrete had sufficiently cured while construction progressed on the floors above. R. Baker & Son was challenged to develop an innovative plan to remove the huge beams safely and efficiently. Taking into account the many complex logistical challenges of the project, Baker engineers determined that beam sections would need to be cut and removed from the structure’s interior, rather from the exposed ends jutting from the building.  After hours of brainstorming, the Baker team came up with a unique and inventive solution that would provide the key to the project: custom-fabricated weighted dollies that would be used to slide the beams inward while serving as counterweights. 

The removal procedure began with Baker team members fabricating steel guides around each I-beam and securing them to nearby concrete columns. After attaching two heavily-weighted dollies to each beam, workers would cut a 4-foot section, each weighing 1,200 lbs., from the interior end of the I-beam. The dollies/counterweights prevented the cantilevered ends of the beams from tipping past the fulcrum point when the sections were detached. Each time a section was removed, Baker crew members used heavy-duty winches to wheel the remaining beam another four feet into the building. Then everything would be repositioned and the entire process would be repeated. The removed sections were stacked three high, and workers utilized an in-house material hoist to lower the 3,600-lb. stacks to ground level. 

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553http://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Demolition Project Goes Underground
Demolition Project Goes Underground

A 175,000 square-foot OTC R&D and production building, constructed in the early 1960s, was undergoing complete interior demolition to be repurposed as a pilot facility. The demolition schedule...
Copper Recycling Offsets Dismantling Project Costs
Copper Recycling Offsets Dismantling Project Costs

A large electrical-mechanical contractor hired R. Baker & Son to perform all of the electrical equipment dismantling and mechanical equipment removal at an old vitamin production facility...
CUP Multi-Phase Selective Demolition Project: Demo by Color
CUP Multi-Phase Selective Demolition Project: Demo by Color

An aging central utility plant serving a large northern New Jersey hospital was due for complete renovation, including the replacement of almost all equipment including boilers, chillers, cooling...
Rigging Safety Guidelines - Industrial Services
Rigging Safety Guidelines

Safety is paramount at R. Baker & Son, which is why we strictly observe all rigging safety regulations, guidelines and procedures on every lift we do. Guidelines for rigging safety: Inspect...
R. Baker Salvages Fixtures for Reuse on Plant Consolidation Project
R. Baker Salvages Fixtures for Reuse on Plant Consolidation

A longtime client approached R. Baker & Son with a plant relocation project in which operations at several partially-occupied buildings were to be moved to a single 200,000 sq. ft. building...
Planning for Rigging & Demo Projects
Safety Planning for Rigging and Demolition Projects

When performing a rigging or demolition project, falling materials, fall hazards, unstable structures, and a variety of other hazards can pose serious risks to both workers and the general public, so...
Rigging Process Equipment Narrow Shaft
Rigging Process Equipment Narrow Shaft

An old R&D facility in Northern New Jersey needed to renovate an area to make way for an important new expansion. Because real estate for needed process equipment was limited, the only area...
Demolition Equipment Maintenance
Demolition Equipment Maintenance SOP

Demolition equipment is always being put to the test. Every quality demolition contractor looks to get quality name equipment at a fair price. Demolition equipment maintenance falls under two...