All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Innovative Plan in Manhattan High Rise Project

56 Leonard Street

By the time construction of 56 Leonard, an iconic new residential skyscraper located in the Tribeca section of Manhattan, wrapped up late last year, all of its 145 luxury units had sold out, some going for prices as high as $48 million. Known as the Jenga Tower due to its stunning and unusual appearance, the glass-encased 60-story building features a staggered silhouette of shifting and varying floorplates, cantilevers, and balconies. Not surprisingly, construction of 56 Leonard was exceptionally complex, even by New York City standards, which was recognized last month when ENR New York named 56 Leonard 2017’s Best Project in the Residential/Hospitality category.  

R. Baker & Son took on one of the challenging project’s early hurdles: the removal of massive steel I-beams cantilevered 25 feet over the roof of an adjacent building. The falsework beams were installed on the 6th floor to provide temporary structural support until the concrete had sufficiently cured while construction progressed on the floors above. R. Baker & Son was challenged to develop an innovative plan to remove the huge beams safely and efficiently. Taking into account the many complex logistical challenges of the project, Baker engineers determined that beam sections would need to be cut and removed from the structure’s interior, rather from the exposed ends jutting from the building.  After hours of brainstorming, the Baker team came up with a unique and inventive solution that would provide the key to the project: custom-fabricated weighted dollies that would be used to slide the beams inward while serving as counterweights. 

The removal procedure began with Baker team members fabricating steel guides around each I-beam and securing them to nearby concrete columns. After attaching two heavily-weighted dollies to each beam, workers would cut a 4-foot section, each weighing 1,200 lbs., from the interior end of the I-beam. The dollies/counterweights prevented the cantilevered ends of the beams from tipping past the fulcrum point when the sections were detached. Each time a section was removed, Baker crew members used heavy-duty winches to wheel the remaining beam another four feet into the building. Then everything would be repositioned and the entire process would be repeated. The removed sections were stacked three high, and workers utilized an in-house material hoist to lower the 3,600-lb. stacks to ground level. 

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553http://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Substation and Mechanical Selective Demolition
Substation and Mechanical Selective Demolition: Out With the Old, In With the Ne

A new pharmaceutical company took over an existing North Jersey facility with plans for major renovation. Design work began immediately, and long-lead equipment was ordered early on. To meet the...
Colossal Claw Revolutionizes Rigging of Sunken Oil Rigs in the Gulf of Mexico
Colossal Claw Revolutionizes Rigging of Sunken Oil Rigs

One of the most striking man-made sights in the Gulf of Mexico is the Versabar VB 10,000, the largest seagoing heavy lift vessel ever built in the United States. Based on Versabar’s smaller...
Kosciusko Bridge Demolition
Kosciusko Bridge Demolition UPDATE

Last March, R. Baker & Son wrote about the demolition of the old Kosciuszko Bridge, which at the time had been scheduled to take place during the summer of 2017. After a few delays, remaining...
industrial air shower and dust removal room
Cleanroom Demolition

Interior and selective demolition projects involving cleanrooms are particularly sensitive when it comes to controlling of particulates, temperature, humidity, and pressurization. R. Baker & Son...
Luffing Jib Tower Crane
Tower Crane Luffing Jib

Tower cranes are commonly used for rigging materials and equipment during the construction of tall buildings. The standard tower crane consists of a base fixed to a concrete pad, the mast, the...
Demolition Construction Site Worker
Coming to a Demolition Site Near You: ZeroG Tool Arm

Ekso Bionics is among several pioneering firms that have developed ergonomic tool arms and bionic exoskeleton devices that can be used to maneuver heavy tools as if weightless in a variety of...
Cleanroom Demolition Contractor in Laboratory
Cleanroom Demolition

Interior and selective demolition projects involving cleanrooms are particularly sensitive when it comes to control of particulates, temperature, humidity and pressurization. R. Baker & Son is...
Ground-Penetrating Radar (GPR)
Ground-Penetrating Radar (GPR) and Demolition

R. Baker & Son recently performed selective demolition at a renovation project at a pharmaceutical plant. One of the Baker Team’s challenges was to make way for new laboratory exhaust...