All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Innovative Plan in Manhattan High Rise Project

56 Leonard Street

By the time construction of 56 Leonard, an iconic new residential skyscraper located in the Tribeca section of Manhattan, wrapped up late last year, all of its 145 luxury units had sold out, some going for prices as high as $48 million. Known as the Jenga Tower due to its stunning and unusual appearance, the glass-encased 60-story building features a staggered silhouette of shifting and varying floorplates, cantilevers, and balconies. Not surprisingly, construction of 56 Leonard was exceptionally complex, even by New York City standards, which was recognized last month when ENR New York named 56 Leonard 2017’s Best Project in the Residential/Hospitality category.  

R. Baker & Son took on one of the challenging project’s early hurdles: the removal of massive steel I-beams cantilevered 25 feet over the roof of an adjacent building. The falsework beams were installed on the 6th floor to provide temporary structural support until the concrete had sufficiently cured while construction progressed on the floors above. R. Baker & Son was challenged to develop an innovative plan to remove the huge beams safely and efficiently. Taking into account the many complex logistical challenges of the project, Baker engineers determined that beam sections would need to be cut and removed from the structure’s interior, rather from the exposed ends jutting from the building.  After hours of brainstorming, the Baker team came up with a unique and inventive solution that would provide the key to the project: custom-fabricated weighted dollies that would be used to slide the beams inward while serving as counterweights. 

The removal procedure began with Baker team members fabricating steel guides around each I-beam and securing them to nearby concrete columns. After attaching two heavily-weighted dollies to each beam, workers would cut a 4-foot section, each weighing 1,200 lbs., from the interior end of the I-beam. The dollies/counterweights prevented the cantilevered ends of the beams from tipping past the fulcrum point when the sections were detached. Each time a section was removed, Baker crew members used heavy-duty winches to wheel the remaining beam another four feet into the building. Then everything would be repositioned and the entire process would be repeated. The removed sections were stacked three high, and workers utilized an in-house material hoist to lower the 3,600-lb. stacks to ground level. 

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553http://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Challenging Duct Demolition
R. Baker & Son Completes Challenging Duct Demolition

A rare malfunction in a large HVAC system caused exhaust ductwork to collapse due to a severe negative pressure condition, and building owners were faced with a dilemma. The 160-ft. duct had to be...
Construction Crane NYC
Counting Cranes to Forecast Construction Growth

Cranes are a familiar sight in New York City and other urban areas, and people who depend on the construction industry for our livelihoods, like those of us at R. Baker & Son, tend to be...
Demolition Contractor in NJ
Demo Protection

Some interior or select demolition projects are complete guts or tear outs where everything must go. Some items need to be identified as not to demolish and remove; this can be done with marking with...
R. Baker Plant Relocation Photo
Plant Relocation Specialists

Relocating a plant can be a complex undertaking, one that requires close coordination, meticulous planning, and good communication among contractors, owners, designers, and facility personnel. A...
Baker Works w/ MEP Engineers to Accelerate Plant Relocation
Baker Works w/ MEP Engineers to Accelerate Plant Relocation

Relocating a plant, whether moving across town or across the country, usually means there will be a lapse in production. The longer process is down, the higher the cost, which is why bringing the new...
Fire Protection - Fire Alarms, in Building Demolition
Fire Protection Requirements in Demolition

Demolition in existing buildings and structures that are attached to or near other structures requires coordination with the client, insurance company, or local jurisdiction to review building safety...
Industrial crane boom hoisting up a suspended load by cables
Rigging Equipment - Plan of Control

In both rigging and demolition equipment is what gets the job done. However, it is intelligent, experienced people that decide on the approach of how things get done and in what progression, which...
Confined Space Warning Sign
Confined Space Construction Rule

OSHA’s definition of a confined space is an area that is large enough for a worker to enter that has limited or restricted means for entry or exit and was not designed for continuous occupancy....