All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Interior Demo: Mid-Project Changes Save Time and Money

Interior Demolition - Wet Saw

Discovering an opportunity for substantial cost savings during a project in progress is always a welcome surprise, which was the case on a warehouse renovation in which R. Baker & Son was tasked with performing the   of the 200,000 sq. ft. building. The building was to become a manufacturing plant with 10,000 square feet of offices occupying one corner and heavy mechanical areas throughout the facility. 

Phase one of the interior demolition project was fairly standard. After careful planning and coordination of utility shutoff, everything within the building’s four outer walls and roof were removed using equipment that included forklifts, loaders, and skid steers brought in through existing loading dock doors. R. Baker & Son also handled reclamation and resale of an existing generator and multiple transfer switches to help offset some of the demolition costs. 

The second phase of demolition was saw-cutting and removal of approximately 50,000 sq. ft. of the concrete floor slab to accommodate the new plant’s underground sanitary and process plumbing. It was during this time that it became clear that, with some careful planning and cutting of an addition 4,000 sq. ft. of slab by the Baker Team, much of the overhead electrical conduit and cable tray could be relocated below ground fairly easily, saving a considerable amount of money in labor and material. Not having racks of conduit suspended from the ceiling or cable tray with miscellaneous steel supports would also result in a much cleaner, more aesthetically-pleasing installation. 

R. Baker & Son worked closely with plumbing and electrical contractors throughout the BIM coordination process for precisely relocating, trenching and backfilling all pipe and conduit. These changes resulted in savings of $112,000 and four weeks were shaved from the overall master schedule. With a tight budget, aggressive schedule and cost overruns in other areas of the project, this was music to the owners’ ears.

Full News Archive

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

rigging project planning, man welding steel beams
Expert Rigging: Meticulous Planning for Safe Lift Projects

A major rigging project demands meticulous planning and execution. While the actual lift may only span a day or two, it represents the culmination of weeks or even months of intense...
Rigging Equipment, skyline NYC, Women Owned Business
Efficient Rigging and Equipment Setup: Planning and Collaboration

R. Baker & Son was contacted by a large mechanical contractor with whom we have worked in the past and who works in the New Jersey-Philadelphia area. They had a large renovation project that...
Environmental Solutions for Dismantling, Decommissioning and Demolition
Eco-Friendly Solutions for Dismantling, Demo & Decommissioning

Demolition, dismantling, or decommissioning of industrial facilities is a complex process that requires meticulous planning and execution. These sites often contain hazardous chemicals, substances,...
Selective Demolition and Rigging at Process Plant
Selective Demolition and Rigging at Process Plant

R. Baker & Son recently performed selective demolition and equipment rigging for a process plant construction project. The selective demolition was necessary to prepare the existing facility to...
Chiller and Cooling Tower Installation at a South Jersey Hospital
Rigging Success: Chiller & Cooling Tower Installation at Jersey Hospital

Recently, R. Baker & Son team was faced with the task of installing a new 1200-ton chiller and double cell cooling tower at a South Jersey hospital. The project was referred to us by a trusted...
Industrial Workers Rigging 2024
Celebrating a New Year from R. Baker & Son

As a new year begins, we reflect on our deep appreciation for all our employees, associates, contractors, vendors, and customers. Our founder, Ruby Baker, started R. Baker & Son in 1935 during...
Define Demolition Scope and Budget
Maximizing Your Demolition Project - Tips to Define Scope|Budget

Often on large construction and renovation projects, the demolition portion of the Scope of Work is vague or poorly defined. It’s not uncommon to see a boxed-out area on drawings with only a...
Demolition in New York,
Industrial Demolition in NYC: A Look at the Process and Impact

When it comes to industrial demolition in NYC, R. Baker & Son has been trusted for well over 80years. With their expertise, experience, and commitment to safety, they have become one of the most...